Procedure for Tower Site Co-Location

The following procedure shall be used for consideration of any request for co-location of equipment on a County facility by a private company.

  1. The applicant shall obtain and complete a Hanover County Tower Co-Location Application FormRequires Adobe Acrobat Reader, which shall include, but not be limited to the following information:
     
    1. The name and address of the person and company/firm making the request.
    2. The name of the company that desires to co-locate equipment on the County facility.
    3. The GPIN and address of the Hanover County tower site  proposed for the co-location.
    4. The reason for the use of that particular facility.
    5. The proposed frequency band of the equipment and a description of the equipment.
    6. The type of antenna to be used and the requested antenna height.
    7. The proposed time line for the project.
    8. A preliminary site design drawing, including any features to be added to the facility or the site of the facility.
    9. A description of any additional utilities, structures or equipment required at the site. 
    10. The name, telephone number, fax number, e-mail address and mailing address of the contact person.
       
  2. After the application has been submitted to the Department of Emergency Communications, the applicant shall:
     
    1. Perform a structural analysis on the facility, analyzing the effect of the proposed additional equipment, and provide the results and a complete written report prepared by a qualified professional, to the County.
    2. Perform an inter-modulation study to assess potential interference issues in relation to the County’s Public Safety Communications System or any other equipment that may be located on the facility, and provide the results and a complete written report prepared by a qualified professional, to the County.
    3. Perform an environmental study of the site, if a new building or structure will be required, and provide the results and a complete written report prepared by a qualified professional, to the County.
    4. Submit a grounding plan to the County.
    5. Enter into a co-location agreement, including provisions for maintenance, with the County.
    6. Obtain a Conditional Use Permit, Building Permit, and any other applicable federal, State or local permits, approvals or licenses.
    7. Pay all costs for the County’s Consultant/Engineer to review the application, advise the County staff and oversee the project on behalf of the County.    A deposit in the amount of the estimated cost of the consultant’s services shall be paid to the County at the time of submission of the first report referred to above, and prior to any County consideration of the application.  If the deposit is less than the amount of all such cost, the applicant shall pay the amount of the shortfall to the County within fifteen days of the date of written request.  If the costs are less than the deposit, the excess amount shall be refunded to the applicant following completion of consideration by the County.

Contact for the Emergency Communications Department: Curtis J. Shaffer - Director, 804-365-6142; cjshaffer@co.hanover.va.us; Emergency Communications Department P.O. Box 470, Hanover, Va. 23069.

Hanover News Release, February 10, 2005 (upd. 9/2011)

     

Hanover County Seal  

 
Copyright © 2011 Hanover County, Virginia. All Rights Reserved.
Hanover County, P.O. Box 470, 7497 County Complex Rd., Hanover, VA 23069, 804-365-6000.
Contact Us | Help Using Web Site
Web Site Information | Legal Disclaimer | Internet Privacy Policy Statement
Problems using this website? Email the web administrator.